Skip to content
HES.
Contact Us
Sectors
Healthcare & HospitalsKeep patients safe and your accreditation secure, with infection, Legionella and AMR risk reducedWater & WastewaterStay in consent, and cut the energy and chemicals it takes to get thereCommercial & FacilitiesMeet your EPC and disclosure obligations while running cost and carbon fallAgriculture & Urban FarmingProtect your yield and soil while using less water and fertiliserPoultry FarmingProve you control the water your birds drink, with clean lines, no pathogens and the evidence in handLocal AuthoritiesMove your estate towards net zero with compliant assets, funded to saveEmerging MarketsBuild investable, accreditation-ready infrastructure on reliable water, sanitation and powerHotels, Hospitality & LeisureKeep guests safe and pools open, with Legionella risk controlled and pool-hall cost cutData CentresCut the cost and water your cooling burns, and harden Legionella control, without touching uptimeFood & Beverage ProcessingCut your trade-effluent bill and hold consent, without touching food safety or uptimeMental HealthKeep the ward safe, with a hand-hygiene option that carries no ingestion, fire or ligature riskJustice & CustodyHand hygiene that is safe to issue inside the wing, where alcohol products are restrictedSocial CareProtect residents and carers, with hand hygiene that is safe to use and kind to skinEducationCut infection-driven absence with child-safe hand hygiene, at a defensible cost across the estateFresh Produce Post-HarvestHold condition from harvest to the customer, and evidence the residue question that now sits with youHousing & Residential BlocksKeep residents safe from the electrical supply faults a five-yearly test cannot catch, every day between inspections
Solutions
Clean WaterControl pathogens, fouling and cost where conventional treatment failsAir & Infection ControlReduce airborne pathogens and infection risk, with no ozoneHand Hygiene & Infection ControlEffective hand hygiene with the alcohol risks removed, where alcohol gel is a liabilityEnergyCut energy and recover it from the systems you already runRenewable ElectricityGenerate power from water flow you already treat, with no new infrastructureAgriculture & SoilUse less water and fertiliser while protecting yield and soilElectrical Supply SafetyA continuous watch on the supply faults a periodic test cannot catch, with alarms and isolation built inPerishable Product LifeHold condition from harvest to the point of sale, and evidence what is left on the crop
Sectors
Healthcare & HospitalsKeep patients safe and your accreditation secure, with infection, Legionella and AMR risk reducedWater & WastewaterStay in consent, and cut the energy and chemicals it takes to get thereCommercial & FacilitiesMeet your EPC and disclosure obligations while running cost and carbon fallAgriculture & Urban FarmingProtect your yield and soil while using less water and fertiliserPoultry FarmingProve you control the water your birds drink, with clean lines, no pathogens and the evidence in handLocal AuthoritiesMove your estate towards net zero with compliant assets, funded to saveEmerging MarketsBuild investable, accreditation-ready infrastructure on reliable water, sanitation and powerHotels, Hospitality & LeisureKeep guests safe and pools open, with Legionella risk controlled and pool-hall cost cutData CentresCut the cost and water your cooling burns, and harden Legionella control, without touching uptimeFood & Beverage ProcessingCut your trade-effluent bill and hold consent, without touching food safety or uptimeMental HealthKeep the ward safe, with a hand-hygiene option that carries no ingestion, fire or ligature riskJustice & CustodyHand hygiene that is safe to issue inside the wing, where alcohol products are restrictedSocial CareProtect residents and carers, with hand hygiene that is safe to use and kind to skinEducationCut infection-driven absence with child-safe hand hygiene, at a defensible cost across the estateFresh Produce Post-HarvestHold condition from harvest to the customer, and evidence the residue question that now sits with youHousing & Residential BlocksKeep residents safe from the electrical supply faults a five-yearly test cannot catch, every day between inspections
Tools
Ask HESCase StudiesInsightsAbout
Contact Us
Energy

Ofgem's Proposed Grid Connection Fees: What Data Centre Operators Must Do Now

3 min read

Ofgem is proposing upfront commitment fees of between £237,500 and £712,500 per megawatt for data centre grid connections. That figure transforms a queue position into a substantial capital event, and operators who cannot evidence credible, lower-energy estate performance now carry greater financial exposure from the moment they apply. The proposal is active as of August 2026, meaning decisions made today about energy performance will directly shape the commercial risk attached to every future connection application.

What exactly is Ofgem proposing and why does it matter to my development costs?

Ofgem's stated purpose is to filter speculative grid connection applications and accelerate serious projects through constrained network capacity. To do that, it is proposing that data centre developers pay a commitment fee before securing access, with the reported range sitting at £237,500 to £712,500 per megawatt. For a meaningful data centre development, that translates the connection stage from an administrative step into a capital commitment that must be justified to investors, boards and lenders.

The practical consequence is that the risk profile of a connection application has changed. A fee at this scale cannot be treated as a sunk cost of doing business. It becomes a line item that demands supporting evidence: evidence that the project is viable, that the demand projection is real, and that the energy footprint of the estate is as efficient as it can be made before the application lands.

How does my estate's energy performance affect my exposure under this proposal?

Ofgem's filter is designed to favour serious, credible projects over speculative ones. An estate that can demonstrate genuine, measured reductions in energy demand presents a stronger case for connection readiness. Lower declared demand at the point of application reduces the megawatt figure against which the fee is calculated, which directly reduces the capital at risk. An estate running at higher consumption than necessary inflates that figure without any corresponding benefit.

Beyond the fee calculation itself, evidenced energy performance strengthens the broader investment narrative surrounding the connection. Regulators, network operators and lenders are all increasingly attentive to whether declared demand figures are credible. An estate that has already acted on efficiency, and can show it through independently verifiable outcomes, is better placed to defend its application and protect the capital committed at connection.

What is the risk if I apply before addressing energy performance on my estate?

The most direct risk is financial. If a developer applies for a connection sized to current or projected peak demand without having optimised that demand first, the commitment fee is calculated against a higher megawatt figure than may ultimately be necessary. That is capital deployed against an inflated baseline, and if the project later needs to be rescoped, the fee already paid does not automatically adjust.

There is also a reputational and procedural risk. Ofgem's stated intent is to remove speculative applications from the queue. An application that cannot be supported by credible evidence of operational or design efficiency may face greater scrutiny, slower processing, or challenge. In a constrained grid environment, delay at the connection stage has compounding consequences for project timelines and the costs attached to them.

What should operators be doing before submitting a connection application?

Operators should treat energy performance as a pre-application obligation rather than an operational afterthought. Establishing a clear, evidenced baseline of energy consumption across the estate, identifying where demand can be genuinely and measurably reduced, and documenting those outcomes before any application is submitted gives the connection case its strongest possible foundation. The fee range reported by Ofgem means there is now a direct financial return to that preparation.

Operators planning new capacity should also consider that the proposal is active now. Timelines for connection applications in constrained areas are already extended, and the window between acting on energy performance and needing to submit an application may be shorter than it appears. Beginning that work immediately, rather than treating it as something to address once planning is secured, is the lower-risk path.

Questions answered

Frequently asked

Does the proposed fee apply to all data centre grid connections or only new builds?

The Ofgem proposal as reported in August 2026 targets access to constrained electricity network capacity. Operators should take advice on whether their specific connection scenario, whether new build, expansion or upgrade, falls within the scope of the proposed commitment fee structure, as the financial exposure varies significantly depending on the megawatt figure attached to the application.

If the proposal is not yet confirmed, should I wait before acting on energy performance?

No. The proposal is active and the direction of travel from Ofgem is clear: connection access will increasingly favour projects that can demonstrate credible, lower-energy demand. Acting on energy performance before the proposal is formally confirmed costs nothing relative to the fee range involved, and positions the estate well regardless of the final regulatory outcome.

How does a reduction in energy demand translate into a lower commitment fee?

The reported fee range of £237,500 to £712,500 applies per megawatt of connection capacity requested. If genuine efficiency measures reduce the declared demand figure in the application, the megawatt total falls, and the fee calculated against it falls proportionally. A verified reduction in estate energy consumption before application submission is therefore a direct mechanism for reducing the capital committed at the connection stage.